alanya,hukuk,bürosu,avukat,dava,danışma,mehmet,aşıkoğlu,mehmet aşıkoğlu,savcı,eski,ceza,ticaret,haciz,alacak,borçlar,Mehemet,Aşıkoğlu,alanya,avukat,hukuk,bürosu,alanya avukat, mehmet aşıkoğlu, alanya hukuk bürosu,Kerim Uysal,Kerem Yağdır,ahmet sezer, mustafa demir, hüsnü sert, jale karakaya, murat aydemir, ayşegül yanmaz
16931
post-template-default,single,single-post,postid-16931,single-format-standard,ajax_fade,page_not_loaded,,side_area_uncovered_from_content,qode-theme-ver-14.2,qode-theme-bridge,wpb-js-composer js-comp-ver-6.13.0,vc_responsive
 

Violation Of The Right To Neighborhood With The Construction Of The Real Estate

Violation Of The Right To Neighborhood With The Construction Of The Real Estate

THE COURT OF FIRST INSTANCE TO

He Must Seek An Injunction.

Plaintiff: A…..

Defendant: B…..

Case: to halt and demolish the construction which is being carried out, to place an injunction for the construction not to proceed.

Legal evidence: Land Registry, discovery,expert examination, witness and other evidence.

Legal legislation: TMK and all kinds of related legislation.

Instructions :

1-defendant, with his own material………… he is in construction on real estate numbered parcels.

2-the place where the construction was done is within the scope of the registration of the title deed despite the warning and warning the defendant continues his construction.

3-therefore, I had to file this lawsuit to stop its construction and to demolish it. I would also like an injunction to prevent the construction from continuing in the future, as it would cause me harm. That way, my victimization will be avoided.

Conclusion and claim : with the acceptance of my case …………… I respectfully supply and demand that the construction of a numbered parcel of immovable be demolished due to the unfair nature of the construction of the defendant and the decision to place an injunction for the defendant not to continue the construction until the conclusion of this case, and to install the costs to the defendant. ……../……../………

Cost Based Value: …………

Plaintiff A…..